European Data Centre - Frankfurt, Germany.
Phoenix successfully completes the second phase of a new Data Centre in Germany.
Phase 1 was for the installation of 33 Racks, containment and the installation, termination and testing of 3360 OM3 fibre optic (LC) terminations and 6240 Category 6a outlets. Phase 1 was completed in three weeks.
Phase 2 was for the expansion of 18 Racks, containment and the installation, termination and testing of 2592 OM3 fibre optic (LC) terminations and 4320 Category 6a circuits. Phase 2 was completed in three weeks.
Included in Phase 2 was the implementation of SAN Refresh and DWDM expansion.
![]() ![]() ![]() |